The construction of a third bridge over the Danube River is to cost EUR 200 – 270 M, according to feasibility studies conducted at four places where it could be built.
Elean Gagov, expert at the Ministry of Regional Development, explained that the option of building a rail line and its price tag were to be discussed in the second stage of the studies.
He informed that the four options for the new bridge were Oryahovo – Bechet, Silistra – Calarasi, Ruse – Giurgiu, and Nikopol – Turnu Magurele.
Bulgaria and Romania have expressed willingness to build as many bridges as possible to connect the poor regions on the two sides of the Danube, seeking to attract investments, increase traffic and help local businesses.
Elean Gagov said that Romanian company Transproekt 2001, which was hired to conduct the feasibility studies for Danube Bridge 3, has drafted three options for bridges for each pair of cities except for Silistra – Calarasi, where the options were two.
Gagov informed that the consultant has also suggested two options for building a tunnel under the Danube River, at Nikopol – Turnu Magurele and Oryahovo – Bechet.
However, the tunnel option was found to be too costly as it would increase the price tag by EUR 70 M.
It is expected that the construction of the third bridge over the Danube River would seek EU co-financing under the 2014-2020 programming period once the place is selected.
The exact location of the third bridge over the Danube River is to become clear in 2 months.